← All training clusters

Colossus

xAI, United States (2024) — 100,000 x NVIDIA H100 SXM (80GB)

One rack

8 × H100 SXM (80GB) per server

8 servers per rack

= 64 accelerators per rack, drawing 44.8 kW (accelerators only)

Rack layout Reported

Colossus uses Supermicro liquid-cooled 4U servers with 8 GPUs each, 8 servers per rack (64 GPUs/rack), grouped into 512-GPU arrays — per Supermicro's and xAI's public descriptions of the build.

The whole cluster — one mark per rack

1,563 racks holding 12,500 servers and 100,000 accelerators.

At roughly 3 m² per rack including aisle space, that's about 4,689 m² of floor — roughly 11 basketball courts. Floor area is estimated: real halls also carry cooling, power, and networking equipment this doesn't count.

Peak capacity98.90 EFLOP/sdense BF16/FP16
Accelerator power77.0 MWTDP x chips x PUE 1.1
Energy / day1,848 MWhat continuous full load
Racks1,56364 accelerators each
Assumed MFU40.0%NVIDIA default

If fully dedicated, this cluster could train...

Known training runTime on this clusterOriginally took
GPT-3 (175B)2.2 hoursduration not published
Llama 2 (70B)5.9 hours35.0 days on 2,048 x A100 SXM (80GB)
Llama 3.1 (405B)11.1 days54.0 days on 16,384 x H100 SXM (80GB)
PaLM (540B)18.0 hoursduration not published
Chinchilla (70B)4.0 hoursduration not published

Hypothetical: assumes the whole cluster runs one job at the vendor-default MFU, with no downtime, restarts, or contention — Estimated. "Originally took" is the run's own reported hardware and duration where published, for contrast.

Source: xAI's own announcement (Sept 2024): Colossus (Memphis, TN) came online with 100,000 NVIDIA H100 GPUs, described at the time as the largest AI training supercomputer in single-cluster operation. xAI has since announced plans to expand Colossus toward 200,000+ GPUs (mixing in H200s); this entry reflects the initial, most solidly reported 100K figure rather than later expansion targets.